MDA were engaged by ADCO Constructions for the full design of Mechanical, Electrical, Hydraulic, Fire & Sprinkler and NCC Section J Energy Compliance Review & Certification on the Pimpama City Shopping Centre project.
The Scope consisted of the following:
- Stage 02 Building A Shopping Centre: ALDI Supermarket, Coles Supermarket, Mini Major, Specialty retail, Storage, Communal Mall Areas, Plant Rooms, Driveways and Carparks
- Stage 02 Building B Tavern: Tavern, Liquor Store, Communal Areas, Plant Rooms, Driveways and Carparks
- Stage 03 Building C: Medical Centre, Communal Areas, Plant Rooms, Driveways and Carparks
- Stage 03 Building D: Drive Thru Food, Communal Areas, Plant Rooms, Driveways and Carparks
- Stage 03 Building E: Drive Thru Food, Communal Areas, Plant Rooms, Driveways and Carparks
Phase 1 Works – Schematic Design
The Schematic Design phase of the works was developing the concept designs in order to obtain client acceptance.
Phase 2 Works – Detailed Design
The Detailed Design Stage of the works was developing the design from Schematic Design through to Detailed Design.
Phase 3 Works – Tender/Construction Documentation
The tender/construction documentation works of this stage was developing the design from Detailed Design documentation through to fully designed and co-ordinated documentation for trade tendering and construction by competent Building Services Contractors.
Phase 4 Works – Construction Administration
The construction phase services for this stage was providing administration duties during the construction activities.